The New SLC Timeline

timeline 1
timeline 2

2014-15

  • Unveiled design of The New SLC Airport Redevelopment Project
  • Broke ground on The New SLC Airport Redevelopment Project
  • Started construction of Rental Car Service Facilities and Quick Turn Around Facility
  • Completed Economy Parking Lot

2016

  • Opened Rental Car Service Facilities and Quick Turn Around Facility
  • Announced addition of North Concourse
  • Redirected Terminal Drive to free-up space for terminal construction
  • Demolished former rental car service facilities and south leg of Concourse E
  • Installed more than 7,000 underground stone columns for seismic stability
  • Started Terminal tunnel excavation
  • Began driving piles for Terminal, South Concourse-west, and Gateway Center

2017

  • Continued driving piles for Terminal, South Concourse-west, and Gateway Center
  • Start construction on Central Utility Plant, Gateway Center, Parking Garage, Terminal, and the west side of the South Concourse
  • Opened new Park and Wait Lot and Touch n' Go Convenience Store

2018-19

  • Break ground on west side of the North Concourse
  • Continue construction on the Central Utility Plant, Gateway Center, Parking Garage, Terminal, and South Concourse-west

2020

  • Unveil Gateway Center, Parking Garage, Terminal, North and South Concourses-west
  • Begin demolition of former parking garage, Terminals 1 and 2, and Concourses A and E

2021-24

  • Build North and South Concourses-east
  • Demolition of Concourses B, C and D
  • Demolition of International Terminal