> > > Pedestrian Bridge Floor Replacement

Construction Projects

Pedestrian Bridge Floor Replacement

Project starts: 4/16/2012
Completion date: 7/06/2012
Estimated budget: $246,700

Monthly Updates

4/11/12
The bid opening for this project was held on March 14, 2012. The apparent low bidder was Wasatch West Contracting. However, the City's Value-Based Procurement Program applied and after review of requested documentation, it was determined that Precision Construction had the more responsible bid. Contract documents are currently being executed with Precision Construction.

5/08/12
A pre-construction meeting was held on April 19, 2012 and a notice to proceed was given at that time. The tile submittals have been approved. The tile has been ordered from the manufacturer. Estimated delivery time is approximately five weeks. Material submittals are currently being reviewed.

6/13/12
The Contractor has completed approximately 70% of the painting. The floor tile has been removed and the new tile is scheduled to arrive on June 22, 2012.

Space for Lease

SLCIA Space for Lease

Find information about available space for lease at Salt Lake City International Airport.


Fast Facts

SLCIA Fast Facts

Fast facts on Salt Lake City International Airport.