> > > Vehicle Shop/Warehouse Restroom Renovations

Construction Projects

Vehicle Shop/Warehouse Restroom Renovations

Project starts: 11/18/2013
Completion date: 02/26/2014
Estimated budget:  $299,500

Monthly Updates:

10/10/13
This project will renovate the restrooms, showers and locker rooms inthe Fleet Maintenance/Warehouse Building located in the North Support area of the area. Work will include demolition, repairs to floor and wall finishes, plumbing/piping repairs, and installation of new plumbing fixtures. The bid opening for this project will be held on October 30, 2013.

01/08/14
The demolition of the restroom hs been completed and the Contractor has placed the new floor slab for the restroom. All underground utilities have been installed. The Contractor is currently installing the HVAC units and has started the framing work.

2/13/14
The contractor has completed the wall framing, sheetrock and tile. Mechanical, plumbing and electrical rough-in work is 90% complete. The epoxy flooring is currently being placed with painting scheduled for the third week of February.

3/13/14
Substantial completion for this project was given on February 26, 2014. The contractor is currently working on punch list items.

Space for Lease

SLCIA Space for Lease

Find information about available space for lease at Salt Lake City International Airport.


Fast Facts

SLCIA Fast Facts

Fast facts on Salt Lake City International Airport.