Asphalt Overlay Program Phase VIII

Project starts: 07/22/2013
Completion date: 09/27/2013
Estimated budget: $668,525

Monthly Updates

01/10/13
This project is in the eighth phase of a continuing program to maintain the Airport's infrastructure. The project will consist of surface preparation, asphalt overlay, and minor drainage corrections to prolong the service life of the Airport's pavement. The primary areas to be overlaid in the project will be miscellaneous roads and parking lots throughout the airport campus. Bid documents are anticipated to be available mid February 2013 pending approval from Airport legal counsel of contrct documents to include an ordinance amending Section 3.24.115, Salt Lake City Code, to clarify application of bid criteria for City funded building improvements and Public Works projects.

02/14/13
No update.

03/14/13
This project is in the eighth phase of a continuing program to maintain the Airport's infrastructure. The project will consist of surface preparation, asphalt overlay, and minor drainage corrections to prolong the service life of the Airport's pavement. The primary areas to be overlaid in the project will be miscellaneous roads and parking lots throughout the airport campus. Bid documents are anticipated to be available mid April 2013.

04/10/13
This project is in the eighth phase of a continuing program to maintain the Airport's infrastructure. The project will consist of surface preparation, asphalt overlay, and minor drainage corrections to prolong the service life of the Airport's pavement. The primary areas to be overlaid in the project will be miscellaneous roads and parking lots throughout the airport campus. Bid documents are anticipated to be available mid May 2013.

05/08/13
This project is in the eighth phase of a continuing program to maintain the Airport's infrastructure. The project will consist of surface preparation, asphalt overlay, and minor drainage corrections to prolong the service life of the Airport's pavement. The primary areas to be overlaid in the project will be miscellaneous roads and parking lots throughout the airport campus. A mandatory pre-bid meeting will be held on May 15, 2013. The bid opening for this project is scheduled for May 29, 2013.

6/20/13
This project is in the eighth phase of a continuing program to maintain the Airport's infrastructure. The project will consist of surface preparation, asphalt overlay, and minor drainage corrections to prolong the service life of the Airport's pavement. The primary areas to be overlaid in the project will be miscellaneous roads and parking lots throughout the airport campus. The bid opening for this project was held on May 29, 2013. The apparent low bidder is Consolidated Paving and Concrete, Inc. Contract documents are being prepared.

9/12/13
The contractor has completed work for the asphalt overlay of Employee Lot #3 and the Police Station along with the Delta Service Road. The next phase of work near the B-C Connector by the Boiler Plant will begin on September 16, 2013.

10/10/13
This project was substantially complete on October 7, 2013. The contractor is currently working on punch list items.

Space for Lease

SLCIA Space for Lease

Find information about available space for lease at Salt Lake City International Airport.


Fast Facts

SLCIA Fast Facts

Fast facts on Salt Lake City International Airport.