SLCgov.com
> > > Apron Reconstruction East of Spots 3 and 4

Construction Projects

Apron Reconstruction East of Spots 3 and 4

Project starts: 07/21/2014
Completion date: 12/12/2014
Estimated budget: $2,825,893

Monthly Updates

9/11/12
This project will construct a portion of the concrete apron between the existing service road and T/W H between spots 3 and 4. Work will include demolition and removal of the existing concrete pavement, excavation, stabilization of the underlying subgrade, construction of new portland cement concrete pavement and miscellaneous airfield lighting adjustments. A 100% design review meeting was held on February 15, 2012. This project has been submitted to the FAA for review and approval and will be bid when AIP funding is available.

10/10/12
No update.

11/6/12
No update.

1/10/13
No update.

2/14/13
No update.

3/14/13
No updae.

4/10/13
No update.

5/08/13
No update.

6/20/13
No update.

9/12/13
No update.

10/10/13
No update.

1/08/14
No update.

2/13/14
No update.

3/13/14
No update.

4/14/14
No update.

05/14/14
This project will construct a portion of the concrete apron between the existing service road and T/W H between spots 3 and 4. Work will include demolition and removal of the existing concrete pavement, excavation, stabilization of the underlying subgrade, construction of new portland cement concrete pavement and miscellaneous airfield lighting adjustments. The bid opening for this project is scheduled for May 21, 2014.

07/31/14
A construction notice to proceed was issued to the Contractor on July 21, 2014. Mobilization has been completed. Saw cutting and excavation of concrete around the perimeter of Phase 1, the area in front of Gate A8 is currently taking place.

09/11/14
Saw cutting and excavation of concrete around the perimeter of Phase 1, the area in front of Gate A8 is 80% complete. Placement of Portland cement concrete pavement is scheduled for the end of this week.

11/7/14
The Contractor is placing portland cement concrete pavement in Phase 2, Stage 1, the area located in front of Gate A8 on Concourse A. Cobble rock and stabilization fabric is being placed in Phase 2, Stage 2, the remaining construction area south of Spot 3.

Space for Lease

SLCIA Space for Lease

Find information about available space for lease at Salt Lake City International Airport.


Fast Facts

SLCIA Fast Facts

Fast facts on Salt Lake City International Airport.